Task Name | Duration | Start | Finish | Predecessors | Resource Names |
پوسته | 11/5 days? | Mon 26/03/07 | Wed 11/04/07 | ||
سنگ زني | 1 day? | Mon 26/03/07 | Tue 27/03/07 | ||
تراش 1 | 1 day? | Mon 26/03/07 | Tue 27/03/07 | بورينگ[40%] | |
تراش2 | 1/5 days? | Mon 26/03/07 | Tue 27/03/07 | 4SS | CNC فرز[24%] |
تراش3 | 1 day? | Tue 27/03/07 | Thu 29/03/07 | 5 | CNC فرز[16%] |
تراش4 | 2 days? | Thu 29/03/07 | Sun 01/04/07 | 6 | CNC فرز[55%] |
كف تراشي | 1 day? | Sun 01/04/07 | Mon 02/04/07 | 7 | بورينگ[12%] |
سوراخ كاري1 | 4 days? | Tue 27/03/07 | Mon 02/04/07 | 8FF | دريل راديال[50%] |
سوراخكاري2 | 10 days? | Tue 27/03/07 | Wed 11/04/07 | 9SS | دريل راديال[50%] |
شستشو | 6 days? | Tue 27/03/07 | Thu 05/04/07 | 10SS | |
انبار | 1 day? | Mon 26/03/07 | Tue 27/03/07 | ||
دنده فاينال درايو | 21 days? | Mon 26/03/07 | Wed 25/04/07 | ||
تراش1 | 3 days? | Mon 26/03/07 | Thu 29/03/07 | CNC تراش[33%] | |
تراش2 | 4 days? | Mon 26/03/07 | Sat 31/03/07 | 14SS | CNC تراش[17%] |
دنده داخل | 7 days? | Mon 26/03/07 | Wed 04/04/07 | 15SS | شيپ روسي |
دنده خارج | 21 days? | Mon 26/03/07 | Wed 25/04/07 | 16SS | هاب 50 |
ارسال براي آبكاري | 1 day? | Mon 26/03/07 | Tue 27/03/07 | 17SS | |
دريافت از آبكاري | 1 day? | Wed 04/04/07 | Thu 05/04/07 | 18SS+7 days | |
ديبور | 6 days? | Wed 04/04/07 | Sat 14/04/07 | 19SS | |
ارسال به انبار | 6 days? | Wed 04/04/07 | Sat 14/04/07 | 20SS | |
فلنچ | 12 days? | Mon 26/03/07 | Wed 11/04/07 | ||
دريافت از فورج | 3 days? | Mon 26/03/07 | Thu 29/03/07 | ||
كف تراشي و سايز | 4 days? | Mon 02/04/07 | Sun 08/04/07 | 23SS+5 days | تراش تبريز |
سايز و مته مرغك | 3 days? | Mon 02/04/07 | Thu 05/04/07 | 24SS | تراش تبريز[50%] |
خشن تراشي | 3 days? | Wed 04/04/07 | Mon 09/04/07 | 25SS+2 days | CNC تراش[50%] |
پرداخت | 3 days? | Wed 04/04/07 | Mon 09/04/07 | 26SS | CNC تراش[80%] |
كف تراشي | 2 days? | Wed 04/04/07 | Sun 08/04/07 | 27SS | CNC تراش[50%] |
سنگ زني | 3 days? | Wed 04/04/07 | Mon 09/04/07 | 28SS | سنگ محور |
دنده زني | 4 days? | Wed 04/04/07 | Tue 10/04/07 | 29SS | هاب 80[50%] |
سوراخ كاري | 5 days? | Wed 04/04/07 | Wed 11/04/07 | 30SS | دريل ستوني |
فرزكاري | 4 days? | Wed 04/04/07 | Tue 10/04/07 | 31SS | فرز يونيورسال[70%] |
انبار | 1 day? | Tue 10/04/07 | Wed 11/04/07 | 32 | |
مهره فلنچ | 8 days? | Mon 26/03/07 | Thu 05/04/07 | ||
فرزكاري | 5 days? | Mon 26/03/07 | Mon 02/04/07 | CNC فرز | |
ارسال به سياهكاري | 1 day? | Mon 02/04/07 | Tue 03/04/07 | 35 | |
دريافت از ساهكاري | 1 day? | Tue 03/04/07 | Wed 04/04/07 | 36 | |
انبار | 1 day? | Wed 04/04/07 | Thu 05/04/07 | 37 | |
درپوش بزرگ | 2 days? | Mon 26/03/07 | Wed 28/03/07 | ||
كف تراشي | 2 days? | Mon 26/03/07 | Wed 28/03/07 | بورينگ | |
سوراخكاري | 2 days? | Mon 26/03/07 | Wed 28/03/07 | 40SS | دريل راديال |
انبار | 1 day? | Mon 26/03/07 | Tue 27/03/07 | ||
درپوش كوچك | 10 days? | Mon 26/03/07 | Mon 09/04/07 | ||
پرداخت | 3 days? | Mon 26/03/07 | Thu 29/03/07 | تراش تبريز | |
سوراخ كردن | 3 days? | Thu 29/03/07 | Tue 03/04/07 | 44 | دريل ستوني |
انبار | 1 day? | Tue 03/04/07 | Wed 04/04/07 | 45 | |
سايز كردن | 3 days? | Wed 04/04/07 | Mon 09/04/07 | 46 | تراش تبريز |
درپوش فلزي | 6 days? | Mon 26/03/07 | Tue 03/04/07 |
Task Name | Duration | Start | Finish | Predecessors | Resource Names |
خار تخت | 150 days? | Mon 26/03/07 | Tue 30/10/07 | ||
تهيه مواد | 1 day? | Mon 26/03/07 | Tue 27/03/07 | ||
ارسال براي سنگ زني | 1 day? | Mon 26/03/07 | Tue 27/03/07 | ||
دريافت از سنگ زني | 1 day? | Mon 26/03/07 | Tue 27/03/07 | ||
فرزكاري1 | 50 days? | Mon 26/03/07 | Wed 06/06/07 | فرز يونيورسال[10%] | |
فرزكاري2 | 50 days? | Wed 06/06/07 | Sat 18/08/07 | 191 | فرز يونيورسال[10%] |
فرزكاري3 | 50 days? | Sun 19/08/07 | Tue 30/10/07 | 192 | فرز يونيورسال[10%] |
انبار | 1 day? | Mon 26/03/07 | Tue 27/03/07 | ||
خارفنري | 26 days? | Mon 26/03/07 | Wed 02/05/07 | ||
تهيه مواد | 1 day? | Mon 26/03/07 | Tue 27/03/07 | ||
سنگ زني | 24 days? | Tue 27/03/07 | Tue 01/05/07 | 196 | سنگ محور |
انبار | 1 day? | Tue 01/05/07 | Wed 02/05/07 | 197 | |
منتاژ پيچ روي فلنچ | 20 days? | Thu 19/07/07 | Sat 18/08/07 | 105FF | پرس هيدروليك |
منتاژ اورينگ روي رينگ | 20 days? | Sat 02/06/07 | Sun 01/07/07 | 129؛136 | اورينگ 4[2] |
منتاژرينگ روي فلنچ | 20 days? | Thu 19/07/07 | Sat 18/08/07 | 200؛199FF | پين چاکدار[1] |
منتاز بلبرينگ روي پينيون | 10 days? | Mon 26/03/07 | Mon 09/04/07 | ||
منتاژ پينيون روي پوسته | 28 days? | Mon 26/03/07 | Sat 05/05/07 | 202SS | کاسه نمد 38*56*10[1] |
منتاژدرپوش روي پوسته | 28 days? | Mon 26/03/07 | Sat 05/05/07 | 203SS | پيچ تخت 10*8[3]؛چسب ماستيک[1] |
منتاژ فلنچ ودنده | 28 days? | Sun 26/08/07 | Sat 06/10/07 | 203SS؛201؛91SS؛145 | |
بستن درب گيربكس | 28 days? | Sun 26/08/07 | Sat 06/10/07 | 205SS | چسب ماستيک[1]؛پيچ تخت 12*3.5[8] |
تست نشتي | 28 days? | Sun 26/08/07 | Sat 06/10/07 | 206SS | بنزين[1] |
رنگ كاري | 28 days? | Sun 26/08/07 | Sat 06/10/07 | 206SS | رنگ سبز[1] |
قلاويز دستي | 28 days? | Sun 26/08/07 | Sat 06/10/07 | 208SS | |
نصب پلاك | 28 days? | Sun 26/08/07 | Sat 06/10/07 | 209SS | |
انبار | 1 day? | Mon 26/03/07 | Tue 27/03/07 |
Resource Name | Type | Material Label | Initials | Group | Max. Units | Std. Rate | Ovt. Rate | Cost/Use | Accrue At | Base Calendar | Code |
Standard Rate: ريال 0/00/hr | 5,800% | ريال 0/00 | |||||||||
بورينگ | Work | ب | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 1111 | ||
فرز يونيورسال | Work | ف | فرز | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | ||
CNC فرز | Work | C | فرز | 200% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | ||
دريل ستوني | Work | د | سوراخكاري | 300% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 1241 | |
دريل روميزي تبريزي | Work | د | سوراخكاري | 300% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 1251 | |
دريل راديال | Work | د | سوراخكاري | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 1231 | |
دريل روميزي چيني 1 | Work | سوراخكاري | 300% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
تراش تبريز | Work | ت | تراش دستي | 500% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 21 | |
CNC تراش | Work | cnc | تراشcnc | 500% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 22 | |
صفحه تراش | Work | ص | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 2311 | ||
Face center | Work | F | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
سنگ چرخدنده سوئيسي | Work | س | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
سنگ چرخدنده تك لبه | Work | س | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
سنگ داخل | Work | س | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
سنگ محور | Work | س | سنگ محور | 400% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 33 | |
سنگ ابزار تيز كن | Work | س | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
سنگ هزار خار | Work | س | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
شيپ 50 | Work | ش | شيپ | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 4111 | |
شيپ 20 | Work | ش | شيپ | 200% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 412 | |
شيپ روسي | Work | ش | شيپ | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 4131 | |
هاب 50 | Work | ه | هاب | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 4211 | |
هاب 80 | Work | ه | هاب | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 4221 | |
هاب افقي | Work | ه | هاب | 300% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 424 | |
شيو | Work | ش | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 4311 | ||
چمفر | Work | چ | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 441 | ||
بروچ | Work | ب | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
جوش | Work | ج | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
پرس 15 تن | Work | پ | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
پرس دستي 2 تن | Work | پ | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
پرس هيدروليك | Work | پ | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
اره نواري | Work | ا | اره | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 5211 | |
اره نواري | Work | ا | اره | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | 5231 | |
كمپرسور باد 1 | Work | ك | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
كمپرسور باد 2 | Work | ك | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
CO2 جوش | Work | C | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
Rolling | Work | R | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard | |||
ليفتراك | Work | ل | 100% | ريال 0/00/hr | ريال 0/00/hr | ريال 0/00 | Prorated | Standard |